A scrum team works on a 4 weeks sprint
Asked by admin @ in Computer Science viewed by 8717 People
Question 14/20
00:06A Scrum Team works on a 4 weeks Sprint. After few Sprints, the team finds that they spend more effort on unit testing, as the code base size has increased. What can be BEST recommendedthis team?Select the correct option(s) and click Submit.Unit testing is not fun anyway. As a self-organized team, choose to ignore the unit testingAdopt practices like test automation from other frameworks like XPIncrease the duration of the sprint from 4 weeks to 6 weeksAdd two more temporary testersForm a separate Testing team